Federal Regulatory Commission Tells Cat Creek to Submit Progress Reports Now

(Last updated on Wednesday, April 13, 2022) – While the Elmore County Commissioners are reconsidering a previous decision to give Cat Creek Energy an extension on the construction of their large energy project, the Federal Energy Regulatory Commission (FERC) told Cat Creek they legally need to file progress reports on the pump storage hydro electrical generating facility portion of the project. The progress report deadline Cat Creek should have submitted expired about two weeks ago or more specifically, March 31, 2022. 

If Cat Creek Energy cannot even be bothered to submit a progress report to the US Government regarding the project they want to build on lands only 20 miles to the northeast of Mountain Home, Idaho, what makes the resident of Elmore County or the Elmore County Commissioners believe Cat Creek will follow through on any of the requirements set forth in the project’s Development Agreement between Elmore County and Cat Creek Energy, LLC. 

Below is a copy of the letter the FERC sent to Cat Creek Energy in April 2022, or download the pdf file at https://catcreek-energy.com/wp-content/uploads/2022/04/FERC_overdue-progress-report-13Apr2022.pdf


FEDERAL ENERGY REGULATORY COMMISSION

Washington, D.C. 20426

April 13, 2022

OFFICE OF ENERGY PROJECTS

Project No. 14655-001-Idaho
Cat Creek Energy and Water Storage Project
Cat Creek Energy, LLC

VIA Electronic Mail

James Carkulis
Cat Creek Energy, LLC
jtc@ccewsrps.net

RE:  Overdue Progress Report

 Dear Mr. Carkulis:
     Article 4 of the successive preliminary permit1 for the above referenced project requires submittal of a progress report every 12 months. According to our records, the progress report due March 31, 2022, has not been filed.
     The failure to timely file a progress report warrants the cancellation of the preliminary permit. This letter constitutes notice under section 5 of the Federal Power Act of the probable cancellation of the preliminary permit no less than 30 days from the date of this letter.
If you have any questions, please contact Michael Tust at (202) 502-6522 or michael.tust@ferc.gov.

 

 Sincerely,

~ Signed ~ 

David Turner, Chief Northwest Branch
Division of Hydropower Licensing

__________________
1167 FERC ¶ 61,046.

 


Originally published on April 13, 2022

 

Thanks,

A Concerned Group of Idaho Residents!

County Commissioners Unwisely Grant Cat Creek Energy an Extension on Their Project

(Last updated on Saturday, April 9, 2022)  – On February 11, 2022, the Elmore County Commissioners granted Cat Creek Energy a new two-year extension to begin construction on their massive energy project in the mountains northeast of Mountain Home, Idaho. This was both a mistake and outside the realm of their responsibilities in our opinion. In short, we believe the development agreement only allows an extension to be granted if the project is likely to be operational in two years. In fact, the project has barely begun the FERC approval process, has no water rights nor environmental impact report.  The list is long but one thing we know is that Cat Creek Energy has consistently failed to meet most deadlines.

The S Bar Ranch has filed the following Request for Reconsideration motion with the county commissioners. A reconsideration public hearing with the county commissioners will be held on Friday, April 15, 2022, at 1:30 pm in the Elmore County Courthouse in Mountain Home. Prior to that public hearing, concerned citizens may file written comments regarding the proposed new extension until Tuesday, April 12, 2022. Comments will also be accepted at the Friday, April 15 hearing.

We hope you will let your Elmore County Commissioners know your thoughts and concerns about this extension. 


Land Use and Building Department

520 East 2nd South Street
Mountain Home, ID 83647
Phone: (208) 587-2142 ext 1256
Fax: (206) 587-2120
www.elmorecounty.org 

Date: March 23, 2022

To: Whom It May Concern

Subject: Notice of Public Hearing

Applicants: Merlyn W. Clark for S Bar Ranch LLC

Case #: Reconsideration of EOA-2022-01

Proposal: S. Bar Ranch appeals to the Elmore County Board of County Commissioners for reconsideration of Extension of Approval granted to CUP-2015-03, CUP-2015-04, CUP-2015-05, CUP-2015-06, and CUP-2015-07.

A public hearing will be held before the Elmore County Board of County

Commissioners (the “Board”) on Friday, April 15, 2022, at the hour of 1:30 p.m.

in the Elmore County Courthouse, downstairs in the Commissioner’s room, 150

South 4th East, Mountain Home, ID 83647, for reconsideration of the extension

of approvals granted to Cat Creek Energy, LLC Conditional Use Permits (CUP-

2015-03, CUP-2015-04, CUP-2015-05, CUP-2015-06, and CUP-2015-07).

 

The Board issued its Findings of Fact, Conclusions of Law, and Order on

February 11, 2022 (following a public hearing on February 4, 2022) for granting

a one-time two-year time extension for the five CUPs as provided for in the

Development Agreement signed on February 9, 2018. S Bar Ranch, LLC, filed a

timely request for the Board to reconsider its Findings of Fact, Conclusions of

Law, and Order and rescind the order for the approval of time extension(s) on

the CUP(s). The reconsideration request is reviewed by the Land Use and

Building Department under Elmore County Code 7-3-12. The Director has

conferred with the Board and the Board has granted a reconsideration hearing.

 

Please review the request and provide your written comments to the

Elmore County Land Use and Building Department, 520 East 2nd South Street,

Mountain Home, ID, 83647, by 5:00 p.m. on Tuesday, April 12, 2022, so your

comments are included in staff report. All interested persons shall be heard at

said hearing and the public is welcome and invited to submit testimony.

Testimony will be limited to reconsideration of extension(s) of the CUP(s).

 

The Elmore County Board of Commissioners is responsible for ensuring

compliance with the Americans with Disabilities Act of 1990 (ADA). Any person

needing special accommodations to participate in the public hearing should 

contact the Elmore County ADA Coordinator, Kacey Ramsauer, 24 hours prior to

the Public Hearing at 208-587-2142 ext. 1254, or email ADA@elmorecountv.org.

 

Sincerely,

 

~~ Signed ~~

 

Mitra Mehta-Cooper, Director


Originally published on April 3, 2022

 