Camas Prairie, Elmore County, Idaho

Category Archives: Reservoir

FERC Request Cat Creek Provide Additional Information by March 8, 2019

The Federal Energy Regulatory Commission (FERC) has requested additional information from Cat Creek Energy, LLC regarding their planned Pumped Storage Hydroelectric Project on Little Camas Prairie. Cat Creek Energy has until March 8, 2019, to answer the questions contained in the “Schedule A” document located at the bottom of this post.

The letter and Schedule A can also be directly downloaded here … http://catcreek-energy.com/download/874/


FEDERAL ENERGY REGULATORY COMMISSION
WASHINGTON, D. C. 20426
February 21, 2019

OFFICE OF ENERGY PROJECTS

 

Project No. 14655-001–Idaho
Cat Creek Energy Generation Facility
Pumped Storage Hydroelectric Project
Cat Creek Energy, LLC

 

James Carkulis
Cat Creek Energy, LLC 398 S. 9th Street, Suite 240
Boise, ID 83702

Subject: Additional Information Request Dear Mr. Carkulis:

After reviewing your successive preliminary permit application filed on November 9, 2018, for the Cat Creek Energy Generation Facility Pumped Storage Hydroelectric Project No. 14655-001 and the comments filed on the application, additional information is needed to continue processing your application. Please provide the information requested in Schedule A within 15 days from the date of this letter.

The Commission strongly encourages electronic filing. Please file the requested information using the Commission’s eFiling system at http://www.ferc.gov/docs- filing/efiling.asp. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, D.C. 20426. The first page of any filing should include docket number P-14655-001.

If you have any questions concerning this letter, please call Karen Sughrue at (202) 502-8556.

 

Sincerely,

~ signed ~

For David Turner,
Chief Northwest Branch
Division of Hydropower Licensing

 


Enclosure:  Schedule A
Project No. 14655-001

 

ADDITIONAL INFORMATION

 

1. In section (iii) of Exhibit 2 of your application, you request a waiver of section 4.81(c)(2) of the Commission’s regulations, which requires the filing of a work plan for new dam construction. S Bar Ranch, LLC, in its motion to intervene and protest, objects to this waiver request.

Section 4.81(c)(3) of the Commission’s regulations allows the Commission to waive the requirements of paragraph (c)(2) upon a showing by the applicant that the field studies, tests, and other activities to be conducted under the permit would not adversely affect cultural resources or endangered species and would cause minor alterations or disturbances of lands and waters, and that any land altered or disturbed would be adequately restored. The federally listed bull trout and its critical habitat are within the proposed project boundary at the Anderson Ranch Reservoir. Neither your permit or the project record clearly describes if you intend to conduct geotechnical studies during the term of the successive permit.

If you intend to conduct geotechnical studies, you must either demonstrate that the studies will not affect cultural resources or endangered species and result in minimal disturbance to land and waters, or file a work plan. In the latter case, the work plan must contain: (i) a description, including the approximate location, of any field study, test, or other activity that may alter or disturb lands or waters in the vicinity of the proposed project, including floodplains and wetlands; measures that would be taken to minimize any such disturbance; and measures that would be taken to restore the altered or disturbed areas; and (ii) a proposed schedule (a chart or graph may be used), the total duration of which does not exceed the proposed term of the permit, showing the intervals at which the studies, investigations, tests, and surveys, identified under this paragraph are proposed to be completed.

2. As explained in your original permit, the proposed project would require a Lease of Power Privilege (LOPP) from the U. S. Bureau of Reclamation (Reclamation) for the use of Anderson Ranch Reservoir. Letters filed by Reclamation on April 4, 2017 and January 31, 2019, indicate that you have begun that LOPP process by receiving approval from Reclamation on October 17, 2016 to be a preliminary leasee for a five- year period. The January 31, 2019 filing also indicates that you have entered into a contributed-funds-agreement contract with Reclamation on May 9, 2017. However both letters indicate that you have not provided the required funding for Reclamation’s review of the project, entered into a preliminary LOPP agreement with Reclamation, or begun conducting the studies required by Reclamation to evaluate project impacts. The letters also indicate that Reclamation does not intend to commit resources to processing your proposed project until the required funding is provided. Reclamation’s January 31, 2019, filing states that if you are still interested in this project that it is critical to initiate these steps to attempt to complete the required LOPP steps by October 16, 2021.

Therefore, please file an update on your efforts at conducting the LOPP process steps with noted in Reclamation’s January 31, 2019 letter.

 

 

Comment on Cat Creek Energy’s Hydro Project by March 20, 2019

Take Action

Low water conditions on Anderson Ranch Reservoir on Aug. 17, 2018.

The Federal Energy Regulation Commission (FERC) is actively soliciting your comments regarding Cat Creek Energy’s “Pump Storage Hydroelectric Generating Facility.” The S Bar Ranch, Chris Stephens and many locals who oppose the entire project hope you will provide feedback to our federal government, too.

The goal is to protect Anderson Ranch Reservoir for the people of Elmore County.

How to File a Comment with the FERC

Go To: https://www.federalregister.gov/documents/2018/11/27/2018-25813/cat-creek-energy-llc-notice-of-successive-preliminary-permit-application-accepted-for-filing-and

Please file comments, motions to intervene, notices of intent, and competing applications using the Commission’s eFiling system at http://www.ferc.gov/docs-filing/efiling.asp

Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp.

FYI: You must include your name and contact information at the end of your comments.

Below, you will find some of the issues we believe the federal government should seriously consider before allowing Cat Creek Energy to build a hydroelectric generating facility on the shores of Anderson Ranch Reservoir.

The more comments the feds receive, the harder they will look at this project.

What is Pump Storage Hydroelectric?

What is this “ Pump Storage Hydroelectric Generating Facility” that Cat Creek Energy (CCE) is trying to build on Little Camas Prairie? In theory, it goes something like this …

  • CCE digs out the shell of a reservoir on the bluffs above Anderson Ranch Reservoir.
  • CCE drills six 15 foot diameter tunnels from that new shell of a reservoir down to Anderson Ranch Reservoir.
  • CCE siphons 100,000 acre/feet of water up those bluffs to fill that new reservoir.
  • Once that phase of the project is completed …
  • CCE will release a large amount of water from their reservoir back into Anderson Ranch Reservoir.
  • That water will be run through turbines located at or near the south shore of Anderson Ranch Reservoir.
  • CCE collects that hydroelectric power and sells it to consumers in Washington, Oregon and California via a maze of transmission lines they plan to construct.

The Problems Associated With the CCE Pump Storage HydroElectric

  1. Water Quality: All local reservoirs have had toxic blue-green algae health warnings issued on them during 2017 and 2018 except Anderson Ranch Reservoir.
    The proposed Cat Creek Reservoir will likely experience a blue-green algae bloom soon after it gets filled. And then, Cat Creek will dump that toxic soup into Anderson Reservoir.
    Many people fish, boat and swim in this water. We think it should be kept clean of any blue-green algae source.
  2. Endangered Species: The endangered Bull Trout thrives in Anderson Ranch Reservoir because of the near constant water temperatures at depth. Cat Creek Energy will dump 1000s of gallons of warm and stagnant water back into Anderson, raising the local water temperature. Studies have suggested the Bull Trout will be adversely affected by this warming.
  3. Water level issues in Anderson: The physical act of removing water from Anderson Ranch Reservoir will affect the lake levels. However, massive summertime evaporation and domestic/agricultural use of the water will surely lower the warm season levels of their reservoir. CCE will then need to siphon additional water out of Anderson during the summer to prevent their reservoir from running dry just when we need that water in Anderson the most. Studies show our kokanee salmon fishery in Anderson will be mightily threatened by the CCE hydroelectric facility.
  4. Electrical Transmission Lines: CCE plans to run many high-tension electrical transmission lines between their different projects. Those lines will likely run from the bluffs above Anderson Reservoir and along the Highway 20 corridor. Many studies show that those massive towers greatly affect tourism and the viewshed.

Please consider giving your feedback to our government about the ill-conceived Cat Creek Energy Project.

Cat Creek Energy Development Agreement with Elmore County Gets its First Amendment

During the Dec. 14, 2018 public hearing.

Spoiler Alert: The county commissioners agreed to give Cat Creek Energy, LLC more time to renegotiate certain water issues at the Dec. 14, 2018 public hearing.

The Hearing

In a nutshell, this is what happened at this 30-minute public hearing. The first amendment of the development agreement between Cat Creek Energy and Elmore County in regards to the mega-energy project slated for our backcountry was approved during a public hearing and deliberations on December 14, 2018.

The approved amendment, however, was merely to give the county and the Gooding-based corporation extra time to negotiate the Water Diversion and Delivery Agreements portion of a joint development agreement. The original date to hammer out the details was December 31, 2018. The new date to agree on those water issues is now officially, June 30, 2019.

If the county and Cat Creek Energy cannot come to an agreement by June 30, 2019, the conditional use permits (CUP 2015-04) will lapse.

There were four individuals who testified against giving Cat Creek Energy additional time to hammer out the agreement and one individual who was neither for nor against the amendment. The interesting thing to know and understand is, Cat Creek Energy did not publicly testify at this meeting. There was one Cat Creek lawyer in attendance and she did not give us any reason for why they require more time. That could be important.

FYI: CUP-2015-04 deals with the proposed Cat Creek Reservoir and its Pump Storage Hydro-electrical Generating Facility.

Reference:

More to Come

Expect a follow-on post regarding this issue where we will discuss some of our thoughts about what happened and what didn’t happen at this and other related public hearings.

The Amendable Portion of the Current Development Agreement (Partial Dev Agreement Only)

With a public hearing scheduled for 1:30 p.m. on December 14, 2018, in the Elmore County Courthouse regarding the possible amendment to the Development Agreement between Cat Creek Energy, LLC and Elmore County coming up soon, we thought you might like to see both proposed amendments and the current document.

The full Development Agreement between Cat Creek Energy, LLC, and Elmore County can be viewed and downloaded here …  CCE_Development Agreement (9-Feb-2018)-10673026_1. or at the direct link to that 37 page document at http://catcreek-energy.com/download/463/

A Snippet of the Development Agreement

DEVELOPMENT AGREEMENT RELATIVE TO CAT CREEK ENERGY, LLC
CONDITIONAL USE PERMITS (CUP 2015-03, CUP 2015-04, CUP 2015-05, CUP 2015-
06, CUP 2015-07)

This Development Agreement Relative to Cat Creek Energy, LLC Conditional Use Permits
(CUP 2015-03, CUP 2015-04, CUP 2015-05, CUP 2015-06, CUP 2015-07) (the “Agreement”) is
entered into this 9th day of February 2018, (“Effective Date”), by and between
Elmore County (the “County”), a political subdivision of the State of Idaho, and Cat Creek Energy,
LLC, an Idaho limited liability company (the “Developer”) (collectively, the “Parties”).

WITNESSETH:

NOTE: WITNESSTH portion of the development agreement between Cat Creek Energy and Elmore County was not included (redacted) in this post because it is not pertinent to the December 14, 2018, public hearing.

NOW, THEREFORE, in consideration of the promises, covenants, and provisions set forth
herein, the Parties agree as follows:

AGREEMENT
SECTION 1. DEVELOPMENT OF THE PROJECT.

NOTE: Section 1 of the development agreement between Cat Creek Energy and Elmore County was not included (redacted) in this post because it is not pertinent to the December 14, 2018, public hearing.

SECTION 2. REQUIRED ENCLOSURES FROM CONDITION NUMBER TWO.

NOTE: Section 2.1 of the development agreement between Cat Creek Energy and Elmore County was not included (redacted) in this post because it is not pertinent to the December 14, 2018, public hearing.


(Current) 2.2. Water Diversion and Delivery. Given the complexities of water diversion and
delivery related to the Project, and in an effort to move the Project forward without further delay,
the County and Developer have agreed to defer the negotiation and execution of all Water
Diversion and Delivery Agreements to a later date, to be heard after notice and public hearing, but
which shall be done prior to December 31, 2018, or the CUP related to water shall lapse.


There are two proposed amendments to section 2.2 of the Development Agreement

Option #1 (Blue Document)

The Parties hereby agree to replace Section 2.2 of the Development Agreement with the
following:

2.2 Water Diversion and Delivery.
          (a) The Developer shall divert and deliver water at a rate of up to 200 cubic feet per
second (cfs) to the County under its water right, in priority, on a continuous flow basis, from
the South Fork Boise River to Little Camas Reservoir by use of Developer’s infrastructure, as
long as (1) the water can be accepted into Little Camas Reservoir, as determined by the
Mountain Home Irrigation District, in its sole discretion; and (2) the water diversion and
delivery does not prevent the Developer from performing its ordinary water operations, which
term is defined as generating electricity via hydro-power or performing ordinary maintenance
of its hydro-power infrastructure and (3) Cat Creek Reservoir stored water is at least 20,000
acre feet. Developer’s duty to divert and deliver water to the County shall be suspended
during any emergency conditions that may exist outside of the Developer’s control. The
Developer agrees to use commercially reasonable efforts not to schedule maintenance work
during the anticipated water diversion and delivery time periods for the County.

          (b) For those years when the County elects to take water delivery under Section 2.2 (a)
above, charges for water diversion and delivery shall be billed to the County based on the
Developer’s actual cost of electricity for pumping the quantity of water diverted and delivered
to the County under its water right. Billing invoices from the Developer shall specify the total
amount of water pumped, diverted and discharged to the Anderson Ranch Reservoir by the
Developer and the total amount of water diverted and delivered into Little Camas Reservoir for
the benefit of the County for the twelve (12) month period in which the County takes water
delivery. The Developer shall invoice the County within ninety (90) days from the end of
water delivery to the County for that water delivery period and provide copies of its electricity
cost and its water diversion records to the County with the annual invoicing. Payment by the
County shall be due and payable thirty (30) days after receipt of the annual invoicing.

(c) The Developer consents to use of its diversion point for diversion of water under the
County’s water right.

(d) The County will inform the Developer, or its designated agent, no less than twenty-four
(24) hours prior to any County request for diversion and delivery of water under its water
right. Provided, however, the County shall be under no obligation to request diversion or
delivery of any water, or accept any water, and any County request for water diversion or
delivery shall be in the County’s sole discretion.

(e) The Developer has withdrawn its pending protest at the Idaho Department of Water
Resources against the County’s application for water permit no. 63-34348. The County has
withdrawn its protest against Developer’s water right application No. 63-34403 filed with the
Idaho Department of Water Resources.

(f) The Developer, the Landowners, the County, and their agents, consultants, and
employees shall act in good faith regarding the County and Developer’s pursuit of a water
permit and license under their respective applications, pending before the Idaho Department of
Water Resources, and shall also act in good faith regarding the County and Developer’s
relationship with the Mountain Home Irrigation District.

(g) Notwithstanding anything in the Development Agreement to the contrary, the
County’s obligations to pay for electricity for pumping expense under Section 2.2(b) of the
Amendment in connection with the diversion and delivery of water by the Developer to the
County under Section 2.2(a), shall be subject to and dependent upon the appropriations
being made in the fiscal year for the diversion and delivery of water by the Elmore County
Board of Commissioners for such purpose.

ALL OTHER PROVISIONS OF THE DEVELOPMENT AGREEMENT SHALL REMAIN
IN FULL FORCE AND EFFECT.


Option #2 (Orange Document)

The Parties hereby agree to replace Section 2.2 of the Development Agreement with the following:

“2.2. Water Storage and Delivery. Given the complexities of water diversion and delivery related to the Project, and in an effort to move the Project forward without further delay, the County and Developer have agreed to defer the negotiation and execution of all Water Diversion and Delivery Agreements to a later date, to be heard after notice and public hearing, but which shall be done prior to June 30, 2019, or the CUP related to water (CUP 2015-04) shall lapse.”

ALL OTHER PROVISIONS OF THE DEVELOPMENT AGREEMENT SHALL REMAIN IN FULL FORCE AND EFFECT.


Take Action / What Can You Do

  • Call or write a letter to the Elmore County Commissioners with a delivery date on or before Dec. 14, 2018 stating why you oppose the amendments shown above.
    Commissioner Wes Wootan (208)599-3131 Commissioner Bud Corbus: (208) 599-1294
    Elmore County Land Use and Building Department
    520 East 2nd South Street
    Mountain Home, Idaho, 83647
  • Attend the 1:30 p.m. public hearing on Dec. 14, 2018.
  • More information about the hearing, phone numbers and mailing address can be found at http://catcreek-energy.com/event-cat-creek-energy-public-hearing-for-amending-the-development-agreement-with-elmore-county/
  • Spread the word about the Dec. 14, 2018 meeting. At least one county commissioners believe that because very few people attend these hearing the issues aren’t important to the residents of Elmore County. If you are viewing this on a computer, there is a Facebook Share button just below this post.

EVENT: Cat Creek Energy Public Hearing for Amending the Development Agreement with Elmore County

 

What It’s About?

Can you attend the public hearing at 1:30 p.m. on Friday, December 14, 2018, at the Elmore County Courthouse regarding the Development Agreement between Cat Creek Energy and “the people”?

The Elmore County Commissioners will accept public testimony regarding the possibility of giving Cat Creek Energy full control of a new domestic water source from the South Fork of the Boise River and Anderson Ranch Reservoir.

We don’t believe handing a Gooding County-based corporation the authority, responsibility, and control over Elmore County’s domestic drinking water is a good idea.

Documentation Regarding This Public Hearing

Currently, there are three documents directly related to this December 14, 201,8 public hearing. You can and should download/read the following.

#1. The Public Hearing Notice: “Dec 14, 2018, Public Hearing Notice – Cat Creek Energy Development Agreement” that can be viewed or downloaded HERE Dec 14, 2018 Public Hearing Notice - Cat Creek Energy Development Agreement or at the direct link found at http://catcreek-energy.com/download/731/

#2. Option #1 (blue document) First Amendment to Development Agreement – 14 Dec 2018 Hearing: It can be viewed or downloaded HERE OPTION #1-First Amendment to Development Agreement - For the Dec. 14, 2018 Hearing or at the direct link found at http://catcreek-energy.com/download/755/

#3. Option #2 (orange document) First Amendment to Development Agreement – 14 Dec 2018 Hearing can be viewed or downloaded HERE OPTION #2-First Amendment to Development Agreement - For the Dec. 14, 2018 Hearing or at the direct link found at http://catcreek-energy.com/download/758/

 

When and Where

1:30 p.m. On Friday, December 14, 2018, at the Elmore County Courthouse in Mountain Home, Idaho.

Address: 150 South 4 East, Mountain Home, ID 83647

Map Link: https://goo.gl/maps/W1vikDroruw

 

Take Action

We believe it is important the residents of Elmore County and anyone who loves our backcountry for it’s abundant recreational opportunities to tell the county commissioners you are opposed to the entire Cat Creek Energy project and you oppose the idea of allowing this corporation to control our future domestic water delivery system.

If you cannot attend this public hearing please call the two Elmore County Commissioners who will make the decision whether to allow the Cat Creek Energy project to move forward.

Commissioner Wes Wootan (208)599-3131

Commissioner Bud Corbus: (208) 599-1294

FYI: Commissioner Hofer has been recused from any decision making authority on the Cat Creek Energy project.

Anyone who wishes to testify, but is unable to attend the 1:30 p.m., Friday, December 14, 2018, hearing, may submit written testimony prior to the hearing by sending it to the:

Elmore County Land Use and Building Department
520 East 2nd South Street
Mountain Home, Idaho, 83647

An easy way to further help us is to share this post with your family, friends and co-workers.

Why Did Cat Creek Energy Decide to Unlink the Project Permits?

All five conditional use permits need to be approved to make the Cat Creek Energy project financially viable.” – Creek Creek Energy Spokesman in 2016

Throughout the permitting process, almost every Cat Creek Energy spokesman testified that all five parts of the project needed to be approved or they couldn’t move forward. The permitting process started in 2015 and ended in 2018.

What We Heard:

They’ll never get federal approval for the power lines in sage grouse territory or water rights for their proposed Cat Creek Reservoir.” – Many people who attended the 2016 and 2017 CUP approval hearings.

 

In 2018, after the Elmore County Commissioners surprisingly approved the five conditional use permits, Cat Creek Energy decided the project really might be financially viable with only a portion (huge wind farm or 590-acre solar plant) getting built out. It’s almost like Cat Creek Energy intended to pull the wool over our eyes while getting the county to approve their mega energy project.

 

Water Rights Problem

Cat Creek Energy has run into significant headwinds in obtaining water rights for their proposed reservoir on Little Camas Prairie. About 20 different private and governmental entities filed separate objections and protests to Cat Creek Energy’s water right permit application they filed with the Idaho Department of Water Resources (IDWR). Elmore County “was” one of those entities that objected to Cat Creek getting their hands on Anderson Ranch Reservoir water.

It’s Unacceptable

We find it suspicious that Cat Creek Energy LLC suddenly found financial viability in a piecemeal approach to their mega-energy complex after the commissioners approved the project and years of saying the CUPs needed to be linked.

We find it wholly unacceptable that Elmore County would allow the project to move forward knowing that the Gooding County-based corporation likely knew they’d never get federal approval for the “pump storage hydro” portion of the project and likely will never get the water rights from Anderson Ranch Reservoir either.

We expect the Elmore County Commissioners to postpone any further approvals of the Cat Creek Energy project until the conditional use permits are once again linked together.

Why? Many residents believed the project would never be able to move forward as a complete project and stopped testifying and paying attention. We’re still paying attention, however.

Reference: Elmore County, Idaho Conditional Use Permits for the Cat Creek Energy Project.

  • CUP-2015-03 / Transmission Lines
  • CUP-2015-04 / Pump Storage Hydro- Electrical Generating Facility
  • CUP-2015-05 / Solar – Electrical Generating Facility)
  • CUP-2015-06 / Wind – Electrical Generating Facility)
  • CUP-2015-07 / Electrical Substation

 

Take Action: Write a letter to the Elmore County Commissioners.

  • Tell them the Cat Creek Energy Project is bad for Elmore County’s big game herds.
  • Tell them Elmore County needs to control our own destiny when it comes to “domestic water issues.”
  • Tell them to relink all five Conditional Use Permits like was originally agreed upon.
  • Tell them our tourism industry will never get established with an industrialized energy complex in our wild and scenic backcountry.

 

Address your letter to:

Elmore County Land Use and Building Department
ATTN: Cat Creek Energy Project
520 East 2nd South Street
Mountain Home, Idaho, 83647

 

Did You Know: The Proposed Power Infrastructure for Cat Creek Reservoir

  • The proposed powerhouse would house twelve 60 MW ternary turbines.
  • The powerhouse would also house additional pump facilities which would utilize the same penstocks feeding the turbine/generators to lift the stored water 840 feet from Anderson Ranch Reservoir for storage in the new Cat Creek Reservoir on Little Camas Prairie.
  • The penstocks would be six 14-16 ft diameter steel pipelines each 2,500 feet long.

Reference: Cat-Creek-Energy-FERC-Application-Nov2018.pdf at … Cat Creek Energy FERC Application - Nov 2018 or at the direct link at http://catcreek-energy.com/download/743/